Cancellation of running job in ESP Schedular.

PostPosted: Tue Mar 05, 2013 3:09 pm
by swati30j
Job A is a request job which is scheduled to run on weekends in ESP Schedular .

Start time of job A is based on the completion of its predecessor job and if it does not complete before 4.55CST.
We manually terminate it at 4.55 CST because prod region go live on 5.30CST

Please let us know the possible solutions for it so that we don't require to manually terminate it in case it crosses 4.55CT.

Any suggestions would be highly appreciated.

Re: Cancellation of running job in ESP Schedular.

PostPosted: Tue Mar 05, 2013 3:19 pm
by enrico-sorichetti
a moderator please lock/delete this topic ...
it is a dangerous clone of
http://ibmmainframes.com/about60465.html

:geek:


hint ...
schedule a job at 5.00 to issue an unconditional cancel , if the job to be canceled is not there nobody will care