Required Plan bind or not

PostPosted: Thu Aug 20, 2009 3:27 pm
by tvssv
Hi,

I've a program A pure cobol program. Its calling Program B which is DB2 program. Do I need to Plan bind the PROGRAM A or not.

Thanks
Tvssv

Re: Required Plan bind or not

PostPosted: Tue Aug 25, 2009 4:23 pm
by bhanu1209
Hi,

Compile the Program A also with the respective plan name.

Thanks,
Bhanu