Hi,

I've a program A pure cobol program. Its calling Program B which is DB2 program. Do I need to Plan bind the PROGRAM A or not.

Thanks
Tvssv
tvssv
 
Posts: 6
Joined: Mon Aug 10, 2009 8:41 pm
Has thanked: 0 time
Been thanked: 0 time

Re: Required Plan bind or not

Postby bhanu1209 » Tue Aug 25, 2009 4:23 pm

Hi,

Compile the Program A also with the respective plan name.

Thanks,
Bhanu