The Requirement is as below:
I have two jobs A and B
B runs on all days
A runs on specific days.Say monday and tuesday.
On Monday and Tuesday I want B to run only after A completes. B is not a direct trigger by A. A is just a dependency for B to run. If I place the depence on B that it runs only after A complets, then the job would be waiting for its dependency on all days.